HomeMy WebLinkAboutResolution - 99-18 RESOLUTION NO. 99 - 18
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF SAN JACINTO
IN SUPPORT OF A
TRAFFIC ENFORCEMENT AND COLLISION REDUCTION PROJECT
FOR RAMONA EXPRESSWAY AND AUTHORIZING
THE PARTICIPATION OF SAN JACINTO POLICE OFFICERS THEREIN.
WHEREAS, the California Highway Patrol has received grant funds from the State of
California for the implementation of a Traffic Enforcement and Collision Reduction
Project, the purpose of which is to conduct a traffic enforcement and public awareness
campaign with the goal of reducing fatal and injury collisions on the Ramona
Expressway.
WHEREAS, a portion of the Ramona Expressway between State Route (SR) 79 (State
Street) and the east city limit of Perris (Rider Street) has been identified as the corridor
for which the Traffic Enforcement and Collision Reduction Project has been
established; and
WHEREAS, a portion of the grant provides for a joint CHPISJPD Special Enforcement
Unit along the Ramona Expressway, and
•.. WHEREAS, the City Council believes that increasing law enforcement through the
Special Enforcement Unit is an important element in improving traffic safety on the
corridor.
NOW THEREFORE BE IT RESOLVED that the City Council of the City of San Jacinto
declares the following:
1. The City Council supports the development and implementation of the
Traffic Enforcement and Collision Reduction Project on the Ramona
Expressway Corridor.
2. Officers of the San Jacinto Police Department are authorized to
participate in the Traffic Enforcement and Collision Reduction Project
during non-duty (overtime) hours.
APPROVED AND ADOPTED this 18th day of March 1999
Ayes: Councilmembers Conner, Good, Smedley, Williams and Mayor Cornett
Noes: None
Abstain: None
Absent: None
Mayor
Attest:
Pamela L. Lee
City Clerk
CERTIFICATION
The foregoing is certified to be a true copy of Resolution No. 99 -_ ___, duly adopted by
the City Council of the City of San Jacinto on the date set forth therein.
City Clerk
State of Califomi■
Business,Transportation R Housing Agency PROJECT NUMBER
Office of Traffic Safety
• Traffic Safety Project Agreement PT9967
PAGE 1 (To be completed by Applicant Agency)
1. PROJECT TITLE: TRAFFIC ENFORCEMENT AND COLLISION REDUCTION (TECR)PROJECT
2. NAME OF APPLICANT AGENCY: CALIFORNIA HIGHWAY PATROL(CUP) 4. PROJECT PERIOD
Month-Day-Year
3, AGENCY UNIT TO HANDLE PROJECT: ASSISTANT COMMISSIONER, STAFF From: 01-01-99
To : 6.30-2000
5. PROJECT DESCRIPTION(Summarize the proposed project plan covering the objectives, method of procedure,evaluation, and end product in
approximately 100words.)
The CUP's San Gorgonio Pass and Riverside Areas in cooperation with the San Jacinto Police Department(SJPD)will conduct a traffic
enforcement and public awareness campaign with the goal of reducing fatal and injury collisions on the Ramona Expressway, The specific project
goal and objectives are: to reduce total reportable traffic collisions along the Ramona Expressway corridor by 25 percent from 20.6 to no more
than 15; to deploy a joint CHPISJPD Special Enforcement Unit (SECT) 104 tittles; to deploy a Special Traffic Education Radar(SPECTER)trailer
26 times; and to conduct an aggressive public awareness campaign which includes production and distribution of 5,000 traffic safety information
brochures, distribution of pre-, mid-, and post-project press releases, and participation in 36 evertes where traffic safety issues on the Ramona
essway and/or the grant-funded SEU effort will be discussed. Project funds provide for CHP enforcement and support personnel overtime;
contractual services of SJPD,and print and promotional materials in support of the public awareness campaign.
6. FEDERAL FUNDS ALLOCATED UNDER THIS AGREEMENT SHALL NOT EXCEED$76,593.00
7. APPROVAL SIGNATURES
A. PROJECT DIRECTOR B. AUTHORIZING OFFICIAL OF APPLICANT AGENCY
Name: M.L. HOWARD Phone;657-7253 Name: O.HELMICK Phone:657-7152
Address: 2555 First Avenue / Address: 2 55 irst Avenue
a/ramento,CA 9 18 / S eni A 95818
g
Si nature: y Date: 12-31-98 Signature: Date: 12-31-98
Title: Chief Title: Commissioner
C. FISCAL OR ACCOUNTING OFFICIAL D. OFFICE AUTHORIZED TO RECEIVE PAYMENTS
Name: MARILYN WONG Phone:375-2741 Name: Accounting Section
Address: 860 Stillwater Road Address: P.O.Box 942899
West Sacramento,CA 95605-1649 Sacramento,CA 94299-WOO
denature: Date: 12.31-98
�`tIC COrnntandcr.Accotmtinf 9 ction
OTS-38(Rev 4l96)
PROJECT NO. P199.§7
PROJECT DESCRIPTION PAGE !
BACKGROUND
A. GENERAL CHARACTERISTICS
The California Highway Patrol (CHP) is an operating department within the Business,
Transportation, and Housing Agency. Its authority and responsibilities are established
in the California Vehicle Code. The overall purpose of the Department, as a principal
criminal justice agency, is to ensure safety, security, and service to the public. This is
accomplished through:
• Collision Prevention. To minimize the loss of life, personal injury, and
property damage resulting from traffic collisions.
• Emergency IncidentlTraffic Management. To minimize exposure of the public
to unsafe conditions resulting from emergency incidents, impediments, and
congestion.
Assistance. To assist other public agencies.
Service. To maximize service to the public in need of aid or information.
As of May 1, 1998, the CHP had 6,751 uniformed and 3,273 nonuniformed authorized
personnel positions. The CHP has responsibility for providing 24-hour-a-day services
every day of the year for over 33 million residents of the State of California and some
21.7 million vehicles.
B. STREETS AND HIGHWAYS
The Department is responsible for approximately 103,089.8 mules of highway. Of
these, 14,139 miles are state highways' and 88,950.8 miles are county roads. In 1997,
approximately 205.1 billion miles were driven on CHP patrolled highways. There
were 1,937 fatal, 65,289 injury, and 121,697 property damage collisions in the CHP's
jurisdiction. As a result, 2,270 persons were killed and 104,307 were injured.
C. OPERATING DEPARTMENTS
The organizational structure of the CHP divides the state into eight field Divisions.
Within these Divisions are 99 Area offices. The CHP Headquarters is locates in
j 'Includes interstate Routes, United States Routes, and State Routes
OTS-38b(Rev. 10196)
SCHEDULE A
PROJECT NO. PT19967
PROJECT DESCRIPTION PAGE 2
Sacramento. The CHP's San Gorgonio Pass Area is located within Border Division
and the Riverside Area is located within Inland Division. The San Gorgonio Pass Area
will be the Office of Primary Interest (OPI) for this project.
D. EXISTING SYSTEM
Road patrol officers are deployed on highway systems within the Department's
jurisdiction according to past traffic collision experience and future projections.
Emphasis is generally placed on the enforcement of collision-causing violations. Public
information and education programs are conducted as resources allow.
I
PROBLEM STATEMENT
This project will address a significant traffic safety problem on the Ramona Expressway. The
Ramona Expressway, which traverses unincorporated and incorporated areas of Riverside
County, is within the jurisdictions of the San Gorgonio Pass and Riverside CHP Areas, and the
San Jacinto Police Department (SJPD). CHP and SJPD Average Daily Traffic (ADT) statistics,
respectively, indicate 10,000 and 16,000 vehicles per day travel this corridor. The Ramona
Expressway is a 14.4 mile section of roadway between the east city limit of Perris (Rider Street)
�.. and State Route (SR) 79 (State Street).
In quantifying the problem using Statewide Integrated Traffic Records System (S WiTRS)
statistics, reportable collisions' for the period April l through March 31 of the years 1993
through 1998 are reported in the following table.
Ramona Expressway, SR 79 to the East City Limit of Perris
Collision Data
04-93 to 04-94 to 04-95 to 04-96 to 04-97 to Total 5-Year
03-94 03-95 03-96 03-97 03-98 Average
Fatal
Collisions 0 1 1 3 4 9 1.8
Total
Killed 0 1 1 4 6 12 2.4
Injury
Collisions 18 18 26 16 16 94 18.8
Total
Injured 44 26 59 37 37 203 40.6
l SWITKS.04-01-1993 through 03-31.1998
t reportable collision is one in which a fatality or injury occurred.
OT5-38b(Rev. 10196)
,t_nLLJULr_ A
PROJECT NO. PT9967
PROJECT DESCRIPTION PAGE 3
7
This project recognizes the importance of the community's shaved responsibility to formulate
solutions to reduce tragic-related deaths and injuries and their societal costs. Through a coalition f
of law enforcement agencies, supported by grant resources, project participants will attempt to
achieve the goal of the project which is to reduce fatal and injury traffic collisions by 25 percent.
ATTE FPTS TO SOLVE THE PROBLEM
i
The Riverside County Transportation Department recommended a number of counter measures
which target the 3 E's (Engineering, Enforcement and Education). They acknowledge that traffic
enforcement will be a significant part of the effort. They also anticipate resurfacing the
pavement, installing new reflective raised pavement markers and additional raised pavement
markers for centerline, providing left and right turn lanes at intersections where practical and
installing warning and guide signs.
The San Gorgonio Pass and Riverside Areas, in conjunction with the San Jacinto Poiice
Department, have directed the efforts of their personnel towards addressing traffic-related !
concerns expressed by members of the community. The roadway has been posted for daytime
headlights. However, utilization of existing resources has met with limited success.
i
PERFORMANCE MEASURES I
Project Goal f
To reduce total reportable traffic collisions along the Ramona Expressway corridor, between the
Perris City limit (Rider Street) and SR 79 (State Street), by 25 percent, from the five-year
average of 20.6, to no more than 15 by March 31, 2000.
Project Objectives
1. To deploy a joint CHPISJPD Special Enforcement Unit (SEU)3 104 times by March 31,
2000.
2. To augment enforcement efforts and encourage voluntary compliance with posted speed
limits by deploying a Special Traffic Education Radar(SPECTER)trailer 26 times by
March 31, 2000.
3CHP will deploy in CHP jurisdiction and SJPD will deploy in SJPD jurisdiction.
OTS-38b(Rev. 10196) _
SCHEDULE A
PROJECT NO, PT9967
PROJECT DESCRIPTION PAGE 4
3. To conduct an aggressive public awareness campaign which includes:
a. Production and distribution of 5,000 traffic safety information brochures by
March 31, 2000.
b. Distribution of at least three CHP/SJPD joint press releases: (1) a pre-project
press release by March 15, 1999; (2) a mid-project press release by September 1,
1999; and(3) a post-project press release by April 15, 2000.
C. Participation in 36 events where traffic safety issues on the Ramona Expressway
and/or the grant-funded SEU effort will be discussed by March 31, 2000.
Note. Nothing in this agreement shall be interpreted as a requirement, formal or informal,that an
officer issue a specified or predetermined number of citations in pursuance of the obligations
hereunder.
METHOD OF PROCEDURE
'%w An 18-month traffic safety project will be conducted which includes SEU augmentation of
visible presence and deployment of an existing Special Traffic Education Radar(SPECTER)
unit. These strategies, coupled with an aggressive public information and education program,
will be used to reduce traffic collisions on the Ramona Expressway. The project will have the
following phases.
Phase I - Planning Phase (January 1, 1999 through March 31, 1999)
• Identify project coordinator(CH? Sergeant) by January 15, 1999.
+ Develop operational plan by February 1, 1999. The plan will include overtime allocations,
special project code to record on time keeping and enforcement documents, and reporting
responsibilities.
• Develop contractual agreement with allied agency (SJPD) by February 1, 1999.
• Schedule weekly SEU details, three officers for four hours,twice a week.
• Locate and schedule use of existing SPECTER units by February 15, 1999, to be used in
conjunction with SEU deployments,as available,
• Project coordinator in conjunction with the participating CHP Area Public Affairs Officer
and their counterpart on SJPD will develop and order print and promotional items including
the traffic safety informational brochure(s).
OTS-38b(Rev. IOM)
PROJECT NO. PT9967
PROJECT DESCRIPTION PAGE 5
I
Phase II - Activity Phase (April 1, 1999 through March 31, 2000)
I
• Deploy SEU details, 104 dates in 52 weeks.
• Deploy SPECTER trailer 26 times. `
• Conduct the public awareness campaign.
Phase III - Data Gathering and Analysis (April 1, 1999 through June 30, 2000).
• Collision and citation statistical information will be collected throughout the project period.
Final SWITRS data will not be available for entire activity phase until approximately July 1,
2000.
Phase TV - Final Report(July 1, 2000)
Begin final report which will be due to OTS by September 1, 2000.
i
METHOD OF EVALUATION
t
The CHP project coordinator will evaluate how well the project goals and objectives were
accomplished by addressing the following questions:
Project Goal
Were total reportable traffic collisions along the Ramona Expressway corridor, between the
Perris city limit(Rider Street) and SR 79(State Street) reduced by 25 percent from the five-year
average of 20.6 to no more than 15 by March 31,2000?
Proiect Objectives J
i
1. Was a joint CHPISJPD SEU deployed 104 times by March 31, 2000?
2. Was an aggressive public awareness campaign conducted which included the following:
a. Production and distribution of 5,000 traffic safety information brochures by
March 31, 2000?
b. Distribution of at least three CHPISJPD joint press releases: (1) a pre-project
press release by March 15, 1999; (2)a mid-project press release by September 1,
1999; and(3) a post-project press release by April 15, 2000?
OT5-38b(Rev. 10196)
SCHEDULE A
PROJECT NO. PT9967
PROJECT DESCRIPTION PAGE 6
C. Participation in 36 events where traffic safety issues on the Ramona Expressway
and/or the grant-funded SEU effort will be discussed by March 31, 2000?
3. Were all the activities outlined in the "Method of Procedure" perforated in accordance
with the project agreement?
4. Was the project cost effective?
STATEMENT OF INTENT
It is the intent of the CHP to continue to work within and encourage participation in coalitions of
entities with responsibilities for, or an interest in, traffic safety. Should the "corridor"approach
continue to produce positive results, it is the intent of this Department to seek funding to address i
traffic safety on other corridors as they are identified.
l
a
OTS-38b(Rev. 10196)
SCHEDULE A-1
PROJECT NO, PT996
ADMINISTRATIVE SUPPORT STATEMENT - Explain what type of priority this project has in your
jurisdiction.
This project is considered by the Department to be of high priority and has the full support of
management.
i
AGENCY CONTRIBUTION - Explain what services or funds are being contributed by your agency in
support of this project.
The CHP's contribution will include, but not necessarily be limited to:
FY-I FY-2 TOTAL
Indirect costs @ 17.38 percent applied
to salary and benefits $4,095 $4,384 $8,479
CUP patrol car mileage @ S.44/mile 2,288 2,288 4,576
Total $6,383 S6,672 513,055
i
1l
k
OZ5-38c(Rev. 10/96)
SCHEDULE B
(Page 1)
DETAILED BUDGET ESTIMATE
PROJECT NO,PT9967
FISCAL YEAR ESTIMATES
FY-I FY-2 FY-3 TOTAL COST
01-01-99 l0 10-01-99 to TO PROIECT
COST CATEGORY 09.30-99 06-30-00
A. PERSONNEL COSTS
CHP Officer Overtime
Enforcement
04-01.99 to 09-30-99
416 hm. @$39.20 $15,891
10-01-99 to 12.31.99 S15,891
208 hrs. @$33.20
01-01-00 to 03-31-00 $7,946 7,946
208 hm @$40.11
8,343 8,343
CHP Serpeant Overtime_
01-01-99 to 09-30-99
72 hrs. @$47.47 3,418 3,418
10-01-99 to 12-31-99
36hrs.@$47.47 1,709 1,709
01-01-00 to 06-30-2000
36 hrs. @ 49.34 1,794 1,794
CHP Non-uniformed Overlime
Clerical 5uopart
01-01.99 to 09-30-99
48 hours @ S22.73 1,091 1,091
10-01-99 to 12-31-99
16 hours @ S22.73 364 364
01-01-00 to 06-3040
32 hours @ S23.87 764 764
Communication Support Overtime
04-01-99 to 09-30-99
24 hours @$28.96 695 695
10-01-99 to 12.31.99
24 hours @$28.96 695 695
01-01-40 to 03-31-00
48 hours @ 30.41 1,460 1,460
Graphic Artist
16 hrs. Q$31.46 503 503
Benefi
Uniformed at 7.268% 1,403 1,439 2,841
Non-Uniformed 12.866% 295 422 717
Total Personnel Costs 523,296 $24,935 548,231
B. TRAVEL EXPENSE
Not Applicable
Total Travel Expense
C. CONTRACTUAL SERVICES
S-TPd OMcer Overtime
Enforcement(includes benefits?
0441-99 to 09-30-99
208 hrs.@ 544.14 59,181 $9,191
10-01-99 to 03-31-00
208 hrs. @ 544.14 $9,181 59,181
Total Contractual Services $9,131 $9,181 518,362
OTS-39d(Rev 9191)
SCHEDULEB
(Page 2)
DETAILED BUDGET ESTIMATE
PROJECT NO. PT9967
FISCAL YEAR ESTIMATES
FY-1 FY-2 FY-3 TOTAL COST
01-01-99 to 10-01-99 to TO PROJECT
COST CATEGORY 09-30-94 1 06-30-00
D. NON-EXPENDABLE PROPERTY
Not Applicable
Total Non-Expendable Property
E, OTHER DIRECT COSTS
Print&Promotional Material $10,000 S10,000
Total Other Direct Costs $10,000 $10,000
F. INDIRECT COSTS
Not Applicable
Total Indirect Costs
TOTAL BUDGET ESTIMATE ALL $42,477 S34,116 $76,593
CATEGORIES
1 .
OTS-38e(Rev 9191)
Z&HEVULL ti-t
PROJECT NO. 1P 9967
BUDGET NARRATIVE PAGF
The California Highway Patrol requires a total of$76,593 to implement the Traffic Enforcement
and Collision Reduction (TECR) project.
PERSONNEL COSTS ($48,231)
Personnel costs provide for 832 hours of CHP officer overtime hours to conduct twice weekly
SEU operations; 144 hours of CHP sergeant overtime for development, supervision, and
administrative duties associated with the project; 96 overtime hours for clerical support to deal
with the additional support requirements; and 96 hours of communications support overtime.
Overtime for a Graphic Artist at the CHP Academy has been included for tasks associated with
developing a logo for the public awareness campaign and the brochure(s).
Employee benefit rates of 7.268 percent for uniformed and 12.866 percent for non-uniformed
employees were used to estimate costs for this category. Overtime benefits include:
Uniformed Non-uniformed
State Compensation State Compensation
Insurance 7.268% Insurance 5.216%
OASDI (Social OASDI (Social Security)
Security) 0.000% 7.650%
Total 7.268% Total 12.866% --
CONTRACTUAL SERVICES($18,362)
Contractual services would cover the cost of the SJPD Officers 416 hours of overtime to
participate in the SEU twice weekly for 52 weeks.
OTHER DIRECT COSTS ($10,000)
r '
A traffic safety information brochure(s) will be developed in support of the public information
and education campaign. Additional print and promotional materials such as posters, pens, and
litter bags will be produced and distributed in support of the Ramona Expressway SEU
deployment and collision reduction effort. j
1
PROGRAM INCOME
3
There will be no program income generated as a result of this project.